top of page

Construction

Building and construction operations may take place on greenfield sites, areas designated for industrial development (often land with an industrial park) or at a site with existing or historic activities. A typical sequence of events at a building site could be as follows: • Permitting; • Site set-up and management, security; • Construction worker camp (if any); • Screening, fencing, setting up temporary offices; • Demolition and site clearance; • Ground works such as excavation, filling and the construction of earth structures e.g. embankments, bunds and cuttings; • Construction of temporary roads, car parks, storage areas; • Construction of foundations and structural works; • Construction of the envelope of the building, principally the external facings, cladding and the fixing of windows; • Mechanical/electrical installations and their interface with civil and building work; • Associated trades i.e. joinery, painting and plastering; • Landscaping reinstatement and habitat restoration or creation; • Start up operations and activities.

Our First Employee

Book Your CSCS Test Book Your Health & Safety Test

Booking your CSCS Card Test - the CITB Health, Safety and Environment Test that is required for a CSCS Card has never been easier!

An activity is an operation or process consuming time and possibly other resources. An individual or work team can manage an activity. It is a measurable element of the total project programme.

The term ‘duration’ refers to the length of time needed to complete an activity.

The term 'path' refers to an activity or an unbroken sequence of activities in a project network. The critical path is the longest sequence of activities through a project network from start to finish, the sum of whose durations determines the overall project duration.

‘Float’ is the time available for an activity in addition to its planned duration. For more information see: Programme float.

‘Free float’ is the amount of time that an activity can be delayed beyond its early start/early finish dates without delaying the early start or early finish of any immediately following activity.

A hanging activity is an activity not linked to any preceding or successor activities.

'Impact' is the effect a change has on an activity or the effect a change to one activity has

on another activity.

Ref Society of Construction Law Delay and Disruption Protocol, 2nd edition, February 2017, published by the Society of Construction Law (UK). https://www.scl.org.uk/resources/delay-disruption-protocol

Earned Value Management Handbook, Published by the Association for Project Management in March 2013 suggests that: ‘…Each work package comprises a number of activities to be performed. Each activity can be assigned to only a single work package. Each activity is a stepping stone towards completion of its parent work package.’

bottom of page